XMight is exhibiting at OCP Global Summit 2026 · San Jose · 12–15 October Meet us →

BACKGROUND

Why these standards now

On 10 July 2024, a single 230 kV transmission fault in Northern Virginia caused roughly 1,500 MW of data-center load to disconnect within seconds — exposing the gap between current rack power design and grid interconnection requirements. Regulators responded: ERCOT NOGRR 282, in force since 1 August 2026, makes voltage ride-through and post-fault active power recovery mandatory for large computational loads. Inside OCP, the Data Center Facility project published an Interface Specification Between Hyperscalers and Utility Grid for Disturbance Performance (V1.0.0, September 2026) that states the same commitment at the point of interconnection.1,2

REGULATORY REQUIREMENTS

Standards XMight's POM implementation is designed against

ERCOT · NOGRR 282

Post-Fault Active Power Recovery

Return to at least 90% of pre-disturbance load within 2 seconds of voltage recovery.3

ERCOT Nodal Operating Guide · NOGRR 282

In force since 1 August 2026

XMight's POM implementation is designed to meet this requirement.

WHERE THIS IS HAPPENING

VRT/PFAPR rules are converging across nine jurisdictions.

ERCOT is the first to publish quantified requirements. Comparable rules are in flight across federal NERC, four US ISOs, Canada, two EU regulators, and Australia.4

Region Authority / TSO Regulation Timeline Why It Matters
US — Federal NERC Reliability Guideline May 2026 + Standards Project RG published May 2026 · FERC submission target end-2026 First federal-level "rack-level energy storage" recommendation; sets floor below ISO/RTO variations
US — Texas ERCOT NOGRR 282 + NPRR 1308 In force since 2026/08 · 0.50–0.80 p.u. continued-consumption step-up 2028/01 ~10% of US DC capacity in ERCOT; first jurisdiction with quantified VRT/PFAPR rules
US — California CAISO Large Loads Technical Requirements (Stakeholder WG) Issue Paper 2026-01 · Straw Proposal April 2026 4.5 GW DC studied in 2025-26; first regulator to name "AI-training pulsating load" as risk class
US — Virginia Dominion Energy Facility Interconnection Reqs. In effect (case-by-case) World's largest DC cluster (NoVa); 2024/07 Fairfax 1.5 GW trip event
US — Central SPP RR 696 (HILL) + HILL FRT v1.0 RR 696 approved 2025/9 · FRT v1.0 2025/8 14-state DC corridor; threshold drops to 10 MW
Canada — Ontario IESO TR for Large Computational Loads v1.0 Published 2026-05-01 · stakeholder feedback to 2026-05-28 First fully-published large-load spec with explicit AIDC naming; strictest FRT envelope in NA
Ireland EirGrid + SONI MPID345 Grid Code Mod. (draft) Draft 2025/11 · Rollout 2026 – 2028 DCs ≈ 22% of Irish national power; first FRT draft to name DCs
Germany VDE FNN VDE-AR-N 4130 + A1 amendment A1 draft 2025/10–11 (revising) Largest DC market in Europe (490+ facilities)
Australia AEMC + AEMO Draft Rule (Large IBL ≥ 30 MW) Final rule mid-2026 APAC's first DC-specific rule; aligns with Texas / Ireland